Carver construction: More demo slated for the week of Oct. 4
A town hall meeting for the Carver Academic Facility renovation is planned for noon to 1 p.m. Friday, Oct. 9, in Haggard Hall Room 253.
Now, on to the work planned for the week of Oct. 4:
- Continue demolition of central corridor (see attached floor plan)
- Begin demolition of east canopy (facing Fine Arts/Art Annex)
- 4 dump trucks to remove excavated material from site (7:30 am to 4:00 pm)
- Crews to work 10 hour shifts (7:00 am to 5:00 pm)
- Site preparation for storm sewer system begins at the southeast corner of the building:
- Excavate trench for pipe.
- Removal of excavated material
- Gravel fill delivered to site.
- Noise, dust, additional truck traffic