Carver construction: Updates for the week of Nov. 1
Carver construction activities for week of Nov. 1:
- Complete demolition of Gym C.
- Continue demolition of gyms A and D.
- Complete grading and filling central corridor.
- Begin testing drilled piles:
- Drilled piles (augercast piling) do not generate the loud hammering, vibrating energy that driven piling generates. Noise will be similar in intensity to previous demolition noise.
- 20 percent of piling will involve short “pin” piles that will create noise similar to jackhammering.
- First phase of piling scheduled to be complete late December/early January.
- Noise, odors, dust, truck traffic, vibrations.
Next week’s activities:
- Complete demolition of gyms A and D.
- Begin drilling “micro” piles in central corridor:
- Equipment noise and diesel fumes. Noise will be similar or less in intensity as previous demolition noise.
- Noise, odors, dust, truck traffic, vibrations.