Carver construction: What to expect June 28 to July 10
Construction continues on the Carver Academic Facility construction project on Western Washington University's Bellingham campus.
The project includes replacement of the building center section with a three-story addition and wrapping the east and south sides with new structure and glass windows and other exterior openings. The project will address urgently needed seismic reinforcement throughout the facility, replace numerous aging building systems, provide improved disabled access to classrooms, labs and offices, and allow for much better use of academic spaces.
Live video feeds of the construction project are from the 草榴社区 Office of Facilities Development and Capital Budget.
Here are the biggest impacts to the 草榴社区 community in the next couple of weeks:
- Pedestrian/vehicular detours remain in place.
- Contractor continues to mitigate noise, dust and other construction impacts as much as possible.
- Welding activities are shielded where possible.
Here's what to expect for the week of June 27:
Central Corridor:
Fireproofing
Rough-in mechanical/electrical/plumbing/fire systems
Priority wall framing
Central Corridor Roof:
Roofing
East Side Addition:
Detail/Decking/Welding
Gym C Addition:
Welded connections of sandwich truss
Structural steel
Place air handling units
1935/1970 Building:
Structural steel
1959 Building/Gym A:
Install roof anchors
And here's what'll be happening during the week of July 4:
Central Corridor:
Fireproofing
Rough-in mechanical/electrical/plumbing/fire systems
Wall framing and set door frames
East Side Addition:
Detail/Decking/Welding
Parapet wall framing
Skylight curbs
Roof drains
Gym C Addition:
Structural steel
Welding/decking
1935/1970 Building:
Parapet framing and sheathing
Roof drains and fall anchors
1959 Building/Gym A:
Install roof anchors
Prep and reinforce shear wall north
For questions/concerns, please contact Dale Krause, construction coordinator, 360-650-4646 or dale.krause@wwu.edu.