Construction Update: Veteran Services and the ²ÝÁñÉçÇø Map Collection
To accommodate the DRS/Veteran Services relocation, the Libraries’ Map Collection is moving from the first floor to the second floor of Wilson Library (Phase 1). To prepare for this move, Wilson 2 East is closed for minor demolition, construction of staff offices, and replacement of carpet and light fixtures. This work will be followed by new paint, new map cabinetry, and furniture. The Map Collection portion of the project is expected to be completed by the start of Fall Quarter 2018.
Once the Map Collection is complete, Phase 2 construction will begin on the first floor of Wilson Library in late August 2018 in preparation for the DRS and Veteran Services move, which is scheduled to be complete by the start of Spring Quarter 2019.
The contractor is setting up the project staging area just south of the Library Presentation area. Pedestrian access will be maintained around the fencing.