The renovation of Fraser Hall has begun. The following work will occur during the next week to 10 days:

  • Interior demolition continues.
  • Abatement of interior mechanical elements begins.
  • Abatement of selected portions of the roof begins, weather permitting.
  • Containers for storage of construction materials will be delivered and set up within the fenced area.
  • Dumpsters for construction debris will be delivered and set up within the fenced area.
  • Two more construction trailers for temporary offices will be set up within the fenced area.
  • The large SSC dumpster will be removed and replaced by a smaller dumpster which will be relocated in parking lot 10G (will not affect parking).
  • Demolition work will begin in the mechanical room of Humanities building.