Working starting at the Campus Services Building April 3 to continue through mid May
Starting April 3 and continuing through May 14, crews will be working on the planter area at the Campus Services Building. This work involves waterproofing the planter and upgrading the concrete deck. During this period, there will be a temporary walkway closure on the east side of the building adjacent to the planter, with the pedestrian path being rerouted to the west side of the Campus Services Building.
Please exercise caution when near the construction zones; we appreciate your patience.
If you have questions or concerns, please contact:
Mark Nicasio, Project Manager – Architect
(360) 650-6296
Or
Mark Wickman, Construction Coordinator
(360) 650-3213